Next Making Tax Digital quarterly update deadline: 7 November 2026.Start filing now

How to fill it in

  1. Open the Gantt Chart sheet and enter the Project, Manager and Start date at the top. If you leave Start blank, the timeline begins at the earliest task start, shown under Timeline from.

  2. Add each task, up to 15, with a Task Name and an Owner.

  3. Enter the Start and End date for each task. Days calculates, counting both the first and last day.

  4. Watch the bars fill in across the 16 week columns for every week the task touches.

  5. Set the Status (Not started, In progress, Complete or Delayed) and the % Done for each task. Delayed tasks show in red.

  6. Check the band for TOTAL TASKS, COMPLETE, IN PROGRESS and END DATE, and the TOTAL row for overall progress.

A Gantt chart shows a project’s tasks as bars on a timeline, so you see what happens when. In this free Excel Gantt chart template you type each task’s start and end date and the bars draw themselves across 16 weekly columns. Delayed tasks turn red, and overall progress is worked out from each task’s % done.

How the bars are drawn

Each of the 16 week columns covers seven days from the project start. A task gets a bar in every week it touches, so even a one-day task still shows on the chart. A task spanning four weeks draws one continuous bar.

If you have not fixed a project start date yet, leave Start blank. The timeline then begins at the earliest task start date and shows it under “Timeline from”, so you can plan first and set the official start later.

Reading the chart

Where to look What it tells you
Red bars Tasks with the status Delayed
END DATE in the band The latest end date of any task, your projected finish
TOTAL row, Overall Progress across the project, weighted by task length
Line under the chart Task counts by status, and tasks outside the 16 weeks

The sheet also flags any task whose end date is before its start date.

Gantt chart or task list?

A Gantt chart is best for planning order and timing, such as a kitchen fit, a shop refit or a product launch. For the day-to-day detail of who is doing what, a list is easier to keep up to date. The project task tracker works well alongside this chart.

Gantt chart template with a 16-week timeline: FAQs

Is this Gantt chart template free?

Yes. It is free to download; you just enter your email address to get the Excel file.

Do I need to draw the bars myself?

No. The bars are filled in by the spreadsheet from each task's start and end dates. Change a date and the bar moves.

How long a project can the Gantt chart show?

The timeline covers 16 weeks from the project start. A line under the chart counts any task that falls partly or wholly outside those 16 weeks, so nothing is hidden by accident.

How is overall progress calculated?

Overall progress is each task's % Done weighted by its length in days, so a 20-day task at 50% counts for more than a 2-day task at 50%.

When it is time to file, use aligned.tax

Keeping your records in Excel? Read our guide to free MTD spreadsheet templates to see how aligned.tax sends your quarterly update to HMRC from an .xlsx file. Free for individuals, see pricing.

Using the Google Sheets copy? Download it as an Excel (.xlsx) file before uploading it to aligned.tax.